Welcome to MABT's Project Page! This section of our website will provide updates and information regarding the following projects:
​​
Freeport Borough Waterline Replacement Project
Freeport Borough Service Line Replacement Project
​
​
​​Project Update - March 20, 2025​
​​
The next step is restoration! Concrete work will be first along with landscaping. Paving will be done as soon as the asphalt plants open.
​
Work will take place during the weekdays from 7 a.m. through 5 p.m. During this time, there will be no parking throughout the work area and traffic will be interrupted. No parking zones will be posted. **If you do not receive a call and are part of the impacted area, please call our office and verify your phone number on file.
​
**Please note - our contractor is required to contact PennDOT every morning since Market Street is a state route. If PennDOT is running plow trucks, work will NOT be permitted by PennDOT for the day.
​
​
​
​​​​​​​​​​​​​​​​​​
​​​​
​
​
​